home bbs files messages ]

Forums before death by AOL, social media and spammers... "We can't have nice things"

   alt.engineering.electrical      Electrical engineering discussion forum      2,547 messages   

[   << oldest   |   < older   |   list   |   newer >   |   newest >>   ]

   Message 1,480 of 2,547   
   Don Kelly to Tom Horne   
   Re: Closed Delta 120/240V 3-phase servic   
   22 Jun 15 19:48:12   
   
   From: dhky@shaw.ca   
      
   On 17/06/2015 8:59 AM, Tom Horne wrote:   
   > On Thursday, February 14, 2008 at 1:16:11 PM UTC-5, phil-new...@ipal.net   
   wrote:   
   >> On Thu, 14 Feb 2008 03:44:25 GMT Don Kelly  wrote:   
   >>   
   >> | The "6 phase " scheme wouldn't cost any more in terms of the transformers   
   >> | and could be done using a bank of 3 single phase pole pigs. However, it   
   >> | would appear that there would be additional costs involved with no net   
   gain   
   >> | as well as a more complex system. Where possible one should avoid adding   
   >> | complexity (KISS).  This doesn't mean that it can't be done but may mean   
   >> | that it shouldn't be done.   
   >>   
   >> So what would you have instead, keeping to the requirement of genuine   
   >> 240 volts at the single phase circuits?   
   >>   
   >>   
   >> | There has been some playing around in the past on the basis that 3 phase   
   is   
   >> | good so maybe 6 or 12 phase is better- tain't so except in some special   
   >> | cases.   
   >> | Where 6 phase has been used is in some urban distribution where there is a   
   >> | savings in terms of space necessary at a given line to neutral voltage   
   >> | because the line to line voltage between adjacent phases is then the same   
   as   
   >> | to neutral. Whether this is still being done is something that I don't   
   know.   
   >> | It also has been used for rectifier supplies in order to reduce harmonics   
   >> | and ripple.   
   >>   
   >> I've wondered if any of those 6-wire transmission lines might be phased   
   >> this way, even if the loads end up being split at the far end.   
   >>   
   >>   
   >> | Your scheme of 480Y and single phase transformers is far better.   
   >>   
   >> So that's the way you would go?  What if the utility says they don't want   
   >> to have the loss of an extra set of transformers with MV -> 480 -> 120/240   
   >> and insist on no more than one transformer per MV -> meter path?   
   >>   
   >> --    
   >> |---------------------------------------/----------------------------------|   
   >> | Phil Howard KA9WGN (ka9wgn.ham.org)  /  Do not send to the address below |   
   >> | first name lower case at ipal.net   /  spamtrap-2008-02-14-1211@ipal.net |   
   >> |------------------------------------/-------------------------------------|   
   > I have been in the electrical craft since Nineteen Sixty Six and I have seen   
   a lot of different service voltages supplied to buildings.  First I am not an   
   Electrical Engineer although I have always been the go to guy on theory   
   questions that the    
   trainees and apprentices come up with.  So I'll just go ahead and admit that I   
   don't understand how you could get a six phase output out of a three phase   
   input.  If it is a delta secondary it can only be corner or center of one   
   phase grounded as the code    
   specifically requires those as the only place the bonding jumper can be   
   connected.  I have worked in manufacturing plants were the delta was   
   ungrounded but elaborate measures were taken to insure that any ground fault   
   was detected well before a second    
   such fault on a different phase had any chance to occur.  You simply cannot   
   connect any delta system to ground on two separate phases or you have a dead   
   fault.  I have yet to see any supply system that allows me to take half phase   
   loads from more than    
   one phase.   
      
   You can have 3 single phase transformers with center tapped secondaries    
   connected on the primary to the HV side (delta preferred) and secondary    
   center taps connected to ground so  that there would be 120V on each    
   pair of adjacent legs but 120/240 between opposite legs. This idea has    
   been used for many years for rectifier supplies   
   Technically speaking it is a 6 phase star (the center tapped single    
   phase setup (edison) can be considered as a 2 phase star (although it is   
   called this only in countries that don't use it.   
   The idea of doing this fordistributioncan have advantages- at higher    
   distribution voltages as the clearances can be reduced.   
   In some areas this is worth while- chopping big holes through heritage    
   trees is not a good idea.  .   
      
   >      
   >   
   > Someone has already pointed out that if you have six secondary windings in a   
   star configuration that they would have to be supplied from six phase   
   distribution or two of each of the secondary windings would have same primary   
   winding exciting them and    
   would therefore be functionally parallel with no phase difference or voltage   
   between them.   
   >   
   > It would seen to me that either 208/120 wye connected supply or a 240/120   
   center tapped phase delta with the resultant high leg on one phase would do   
   what is needed.  Either would give you Three phased power for elevator motors,   
   air conditioning    
   chiller or whatever the bigger Three phased load is.   
   >   
   > As to actually insisting that individual units have 240 volt, Three phase, I   
   have yet to see a situation were that is actually needed.  Any Three phase   
   heat pump, air conditioner, or other motor load that will run on 240 volt   
   three phase that I have    
   had to install could be re-tapped to run on 208 Three phase or the motors were   
   labelled as 240,208 Three phase that would run on either without   
   modification.  Even single phase home appliances will run on either in most   
   cases.  Why then would one need to    
   have actual 240 volts in single or Three phase all the way to the individual   
   unit.  I have never actually seen Three phase power run to the individual   
   units of an apartment building.   
   >   
   > If you actually must have 240 volts to each unit in the original posters   
   small apartment building; although no one has explained why that might be   
   true; then you will need either a single phase supply or a separate branch or   
   feeder to each unit for the    
   240 volts.  I have seen existing buildings with Fourteen units with single   
   phase supply but I have not seen any new construction wired that way in the   
   last several decades.   
   I live in an area where air conditioning loads are light and the supply    
   to the transformers on the street is 7200V line to neutral- only one    
   feed from the nearby 3 phase line is taken down  this street- hence    
   120/240 single phase supply to each home.   
   There are rural lines  that are single phase.  13-15 KV line to neutral,   
   ground return (actually a  grounded neutral  wire is also used)  is    
   common.  You are right in that generally new construction will have    
   120/208 in the units- as the  load density is sufficient to warrant it.   
      
      
   >       
   >   
      
   [continued in next message]   
      
   --- SoupGate-Win32 v1.05   
    * Origin: you cannot sedate... all the things you hate (1:229/2)   

[   << oldest   |   < older   |   list   |   newer >   |   newest >>   ]


(c) 1994,  bbs@darkrealms.ca